Complete daily maintenance knowledge of jaw crusher
1. Pre-shift Daily Inspection (Before Startup)
- Check the tightness of all fastening bolts, especially the jaw plate, toggle plate, bearing seat and foundation anchor bolts. Tighten loose bolts immediately.
- Inspect wear parts: movable jaw plate, fixed jaw plate, side liners, toggle plate and toggle seat. Check for cracks, severe abrasion or chipping. Replace components when wear exceeds the limit.
- Check lubrication system: confirm the oil level of bearings is within the standard range. Check grease quality, no deterioration, impurity or water mixing. Check oil pipe and grease nipple for blockage or leakage.
- Check the clearance of discharge opening, verify it meets the required particle size. Remove any foreign materials (iron block, steel bar, wood) inside the crushing cavity.
- Check the transmission part: check V-belts for cracking, aging, slack or uneven tension. Check flywheel and pulley for abnormal cracks. Guard safety protective cover must be intact and firmly fixed.
- Check electrical system: cables, switches, grounding device, emergency stop button. Ensure no exposed wire, short circuit risk. Check dustproof and waterproof condition of motor.
- Check auxiliary equipment: feeding chute, receiving hopper, sealing plates, dust removal device. Remove accumulated materials to prevent blockage.
2. Maintenance During Operation
- Monitor running sound: normal operation has stable mechanical sound. Stop immediately if there appears sharp metal impact, continuous knocking or rumbling noise.
- Monitor bearing temperature: bearing temperature shall not exceed 70℃. If overheating occurs, stop the machine to check lubrication, bearing damage or overload problem.
- Check vibration: observe abnormal violent vibration of the main machine. Do not continue operation when vibration exceeds standard.
- Feed evenly: strictly forbid oversized raw materials and uncrushable metal objects entering crushing chamber. Keep feeding material distribution uniform, avoid unilateral feeding.
- Check discharge status: monitor discharge particle size and output. If particle size becomes coarse, check jaw liner wear and discharge gap.
- Do not perform cleaning, repair or adjustment work while the equipment is running. Never reach into crushing cavity with hands or tools.
- Regularly replenish lubricating grease according to specification during continuous operation.
3. Post-shift Daily Maintenance (After Shutdown)
- Stop feeding first, run the crusher until all materials inside crushing cavity are fully discharged, then shut down the host motor.
- Clean the whole machine: clear accumulated materials on the frame, hopper and surrounding area. Clean dust on motor and bearing housing. Do not use high-pressure water to directly wash motor and electrical components.
- Recheck wear parts, record wear condition for maintenance plan.
- Inspect lubrication points, replenish grease if needed; handle oil leakage in time.
- Check V-belt tension, clean dust between belts.
- Check all safety guards, reset protective parts if they are displaced.
- Check pipeline and dust removal system, clear blockages.
- Fill in daily maintenance log: record running time, abnormal phenomenon, parts inspection and maintenance work.
4. Periodic Maintenance (Based on Working Hours)
Weekly Maintenance
- Comprehensive re-tightening of all bolts
- Full inspection of toggle plate, toggle seat and spring assembly
- Deep cleaning of lubrication pipelines, test grease circulation
- Inspection of bearing clearance
Monthly Maintenance
- Measure wear thickness of jaw plates and side liners
- Check bearing internal clearance, check for pitting or corrosion
- Inspect frame, check for weld cracks at stress points
- Test motor insulation, check cable aging
- Calibrate discharge opening gap
Quarterly / Seasonal Maintenance
- Replace bearing lubricating grease completely
- Disassemble and inspect toggle plate assembly
- Check flywheel and pulley key connection
- Inspect foundation concrete for cracks, re-grout if foundation sinks
Annual Overhaul
- Full disassembly of main body
- Replace seriously worn bearings, jaw liners and toggle plate
- Check eccentric shaft for bending, abrasion and fatigue cracks
- Repair or weld frame cracks
- Complete inspection and maintenance of the whole electrical control system
5. Lubrication Maintenance Specifications
- Bearings adopt high-quality lithium-based grease. The grease filling volume accounts for 1/3 ~ 2/3 of bearing housing space. Too much grease will cause overheating.
- Replace grease completely every 3–6 months. Clean bearing chamber with clean kerosene before refilling.
- Keep grease storage environment clean, prevent sand, dust and water mixing into grease.
- In low-temperature environment, select low-temperature type grease; for high-temperature heavy-duty working condition, use high-temperature resistant grease.
6. Common Fault & Maintenance Notes
- Metal impact sound inside crushing cavity: foreign hard objects enter cavity, jaw liner loose, toggle plate fall off. Stop and inspect immediately.
- Bearing high temperature: insufficient grease, grease contamination, bearing damage, eccentric shaft misalignment, overload feeding.
- Output drop, coarse discharge: jaw plate serious wear, feeding uneven, discharge gap too large.
- V-belt slipping: belt aging, insufficient tension, overload feeding. Adjust tension or replace belts in groups.
- Abnormal vibration: loose foundation bolts, unbalanced flywheel, eccentric shaft bearing damage.
7. Safety Principles for Maintenance
- Cut off the power supply and hang maintenance warning sign before any overhaul work. Lockout-tagout (LOTO) operation is mandatory.
- Do not use hand to take materials inside crushing cavity; use special tools.
- When disassembling heavy parts (jaw plate, toggle plate), use professional lifting tools, avoid casual hoisting.
- After maintenance, check that all tools and sundries are removed from equipment before restarting test run.
- Operators must wear protective equipment: safety helmet, protective goggles, anti-slip shoes.
8. Long-term Shutdown Preservation
- Clean all materials and dust on the whole machine.
- Apply anti-rust grease on machined surfaces, eccentric shaft, bearing parts.
- Loosen V-belts to eliminate long-term tension.
- Cover the equipment with waterproof and dustproof tarpaulin.
- Check anti-rust condition regularly.